Trials of LNG fuel system on Glen Sannox ferry postponed

Ferguson Marine said cooling the pipes to load the fuel is taking longer than expected.

Trials of LNG fuel system on Glen Sannox ferry postponedPA Media

Trials of the liquified natural gas (LNG) system on the delayed ferry Glen Sannox have been postponed as it is taking longer than expected to load the fuel onboard.

With the deadline for handover approaching on September 30, the state-owned shipyard Ferguson Marine has had to push back its LNG harbour trials which were due to begin on Wednesday.

The Scotsman reported the process of cooling the pipes to the sub-zero temperatures necessary to load the fuel is taking longer than anticipated.

Both Glen Sannox and sister vessel Glen Rosa were designed from the outset to be “dual fuel” ferries, able to run on both traditional marine gas oil and LNG.

However problems with installing the LNG system have been behind some of the repeated delays in delivering the two ferries, with the shipyard dealing with these issues over the past year.

A Ferguson Marine spokesperson said: “LNG harbour trials were due to begin on Wednesday with the loading of LNG at quayside.

“However, it is taking longer than initially advised to cool the pipes to the required temperature to load the LNG.

“The additional cooling time needed means the trials will be rescheduled.

“Once the required temperature has been reached, the schedule will be redefined, with new dates likely to be agreed before the end of this week.”

Ferguson Marine said the official handover date remains September 30, though this could be pulled forward if sea trials are successfully completed.

Current cost estimates for Glen Sannox are between £145.5 million and £149.1 million and it is hoped the cost of Glen Rosa will be kept below £150 million.

Now six years late, the total bill will be three times the original £97 million price tag.

David Tydeman, who was chief executive of Ferguson Marine until March, told the newspaper that loading LNG is a “complicated” process involving purging the pipelines of any moisture.

He said: “The time needed to do this was highlighted by the team to me 12 months ago.”

Glen Sannox undertook sea trials earlier this year, but in those tests the 102-metre vessel was not using LNG.

STV News is now on WhatsApp

Get all the latest news from around the country

Follow STV News
Follow STV News on WhatsApp

Scan the QR code on your mobile device for all the latest news from around the country

WhatsApp channel QR Code