West Highland Line reopens following £13m upgrade

The railway links communities in the Highlands and Central Belt, while also carrying thousands of visitors each year to popular tourist spots.

West Highland Line reopens following £13m upgradeSTV News

One of Scotland’s most famous railway routes has reopened following £13m worth of upgrades to help keep the line running safely and reliably.

The West Highland Line dates back more than a century, connecting the central belt to the Highlands, taking thousands of visitors each year to some of Scotland’s most popular tourist spots.

Over the past ten days, up to November 17, passengers have had to let the bus take the strain for the 60-mile section between Crianlarich and Mallaig, allowing up to 100 Network Rail staff to work on upgrading various elements of the line.

Teams of engineers have been working at locations between Helensburgh, Fort William and Mallaig to renew parts of the track, improve drainage and maintain key railway structures.

Project manager Scott McMurchieSTV News
Project manager Scott McMurchie

Project manager Scott McMurchie told STV News: “The track itself has been quite challenging to get to, purely because of the mountainous area of geography that we have. We’ve had to erect temporary scaffolding to get access to the site on the viaduct, which is a Grade B-listed structure.

“We’ve also got tight radius curves, particularly through tunnel 117, so we’ve installed a check rail to protect train services there. We’ve installed composite sleepers, which are recyclable material, to meet carbon footprint targets.

“Teams can mobilise and do a bigger volume of work in a short period. We’re demobilising them and moving on again, reducing the maintenance impact.

A view from above the West Highland Line during worksSTV News
A view from above the West Highland Line during works

“The longevity of the assets we’re installing means that we’re less likely to return to do so much intrusive maintenance work in future.”

The works were carried out to tackle wear and tear across the route, make the railway more resilient to the impacts of severe weather and reduce the likelihood of infrastructure-related delays and restrictions.

The project included renewing more than 4km of worn track at locations between Helensburgh and Mallaig, improving drainage and renewing culverts, vegetation clearance and refurbishing Fassfern Bridge near Spean Bridge and removing a redundant bridge near Loch Eil.

Network Rail has carried out upgrades costing over £13mSTV News
Network Rail has carried out upgrades costing over £13m

Gerry McQuade, capital delivery director at Network Rail Scotland, said: “The West Highland Line is one that people really depend on, whether they’re travelling to work, visiting family or exploring some of Scotland’s most spectacular scenery. This work is about making sure the route continues to provide a dependable service for the communities and visitors who use it every day.”

Mark Ilderton, ScotRail service delivery director, said: “The West Highland Line is an important lifeline for the communities it serves and one of the most iconic railway routes in Scotland, so this significant investment by Network Rail is very welcome.

“The investment will help improve the resilience and reliability of the railway, supporting the communities, businesses and visitors who depend on the West Highland Line for many years to come.”

STV News is now on WhatsApp

Get all the latest news from around the country

Follow STV News
Follow STV News on WhatsApp

Scan the QR code on your mobile device for all the latest news from around the country

WhatsApp channel QR Code

Today's Top Stories

Popular Videos

Latest in Highlands & Islands

Trending Now