Wingas, a joint venture between Germany's Wintershall
Drilling and construction at Saltfleetby is expected to take 30 to 36 months, according to DECC, and the facility would be one of the largest in Britain.
"As the UK becomes increasingly dependent on imported gas, this Government has made it a priority to ensure secure gas supplies," energy minister Charles Hendry said.
"We will introduce measures in the Energy Security and Green Economy Bill to encourage not only more gas storage, but greater gas import capacity to help ensure that our market will deliver gas when it is needed."
The Saltfleetby storage facility is expected to take gas from the Theddlethorpe terminal and increase Britain's gas storage capacity by 15 percent, DECC said.
Britain has a lower ratio of storage as a percentage of demand than France or Germany which can store about a quarter of their annual needs, prompting calls for more capacity to be built to buffer against unexpected supply cuts like those caused by a Russia-Ukraine gas dispute two winters ago.
"We are convinced that the UK needs more storage facilities, in particular seasonal storage, as UK gas production continues to decline," Frank Tauchnitz, managing director of Wingas Storage UK, said.
"The existing storage facilities can cover just 4 percent of the annual gas requirements."
Wingas expects to make a final investment decision on the project in a few months.
Centrica's
(Additional reporting by Daniel Fineren, editing by Anthony Barker)
(c) Reuters 2012. All rights reserved. Republication or redistribution of Reuters content, including by caching, framing or similar means, is expressly prohibited without the prior written consent of Reuters. Reuters and the Reuters sphere logo are registered trademarks and trademarks of the Reuters group of companies around the world.